Update for Day 14, June 9th of the Single Family HOA Roadway Repaving Project.   

 

The Contractor has completed Whisperwood today which COMPLETES the paving of all the roadways.  Traffic cones have been placed at the entrance to Whisperwood to limit entry. As was done for the other roadways, no traffic will be permitted on the roadways for 24 hours after completion. Please don’t have any contractors or deliveries (large trucks) use Whisperwood on Saturday.   

 

If you must drive on the roadway tomorrow, please be careful. Remember, do not turn your front wheels of your car while stopped on the fresh pavement as that will leave a mark.

 

The only remaining work to be done are: correction of the water pooling on Barclay north entrance south side; completing the termination of the underground conduits at each cul-de-sacs; painting of the traffic stop lines (preliminary done next week, final done in two weeks); and installation of the roadway center line markers. All the work should be completed in the next two weeks. 

 

If you have any questions or concerns about the work, please contact either Bob Polizzotto (239-287-1358) , David Lee (239-289-9046) or Mitch Dario (239-431-7803.

 

Thank you,

 

The Strand Single Family HOA Board of Directors