Bennington Roundabout Project

[Bennington STP 1000(23)]

News & Updates

Winter 2025 – 2026

Table of Contents


  • Project Purpose & Need
  • Why a Peanut‑Shaped Design?
  • How to Navigate the VT 67A Roundabout
  • Truck Navigation
  • Roundabout Visualization Video
  • 2025 Construction Season Highlights
  • Current Conditions & What to Expect
  • 2026 Construction Season Plans
  • Stay Informed
  • Contact Information


Project Purpose & Need

The Vermont Agency of Transportation (VTrans) is undertaking major improvements at the intersections of Vermont Route 67A (VT 67A) with Silk Road/Matteson Road, and VT 67A with College Drive to enhance safety, mobility, and access for all users. The central feature of the project is the construction of the new single‑lane peanut‑shaped roundabout to replace the two closely spaced intersections. The project also includes upgraded pedestrian and bicycle facilities, improved drainage and stormwater management, new lighting and landscaping, and roadway reconstruction along each approach.

This area has a long history of crashes due to limited sightlines and high vehicle speeds along VT 67A. The intersections were first identified as high‑crash locations in the mid-1980s and were reassessed several times in the years that followed. Multiple scoping studies and VTrans reviews explored both interim and long‑term solutions, ultimately selecting a roundabout design. In 2021, designers were hired to develop the single‑lane peanut‑shaped roundabout now under construction. This design supports continuous low‑speed traffic flow, reduces crash severity, eliminates left‑turn conflicts, shortens pedestrian crossings, and improves visibility for all users.

The purpose of this project is to improve overall safety at the VT 67A intersections with College Drive, Matteson Road, and Silk Road; reduce vehicle speeds along VT 67A; improve sight distances for safer turning movements; enhance pedestrian and bicycle accommodations; and increase safety at the VT 67A pedestrian crossing.

Click here to read the full Project Announcement for additional background and history.

Why a Peanut-Shaped Design?

A peanut‑shaped roundabout was selected over a circular or oval design because it better fits the layout of the project area. The new VT 67A roundabout replaces two closely spaced intersections—VT 67A at College Drive and VT 67A at Matteson Road/Silk Road. Because of the distance between these intersections, a circular roundabout would have created long straight sections along VT 67A, allowing drivers to speed up and reducing the safety benefits of a curved design.



To prevent this, VTrans and the project designers maintained curvature between the two intersections. These curves help keep vehicle speeds down and provide additional turning and tracking space for larger vehicles entering from College Drive, Matteson Road, and Silk Road. While truck traffic from Silk Road is limited due to the covered bridge, Bennington College, located off College Drive, has regular truck traffic, making this added maneuvering space essential.

How to Navigate the VT 67A Roundabout

Drivers should slow to 25 mph when approaching and traveling through the roundabout. All approaching vehicles must yield to traffic already in the roundabout and enter only when there is a safe gap. Once inside, drivers should travel counterclockwise (to the right) and use their turn signal when exiting. Roadway signage, along with the mountable and splitter islands, are in place to guide drivers in the correct direction around the roundabout. Pedestrians and cyclists have the right of way at the crosswalks on College Drive, VT 67A, and Silk Road.


As the community adjusts to the new single‑lane peanut‑shaped roundabout, drivers are urged to use caution, reduce speed, and follow all posted signs throughout the project area. A roundabout visualization video is included further down in this newsletter to show how traffic is expected to move around the roundabout.


Truck Navigation

Truck traffic was factored into the design of the new VT 67A roundabout. The stamped concrete truck apron along the edge of the center roundabout allows trucks, buses, and emergency vehicles to drive up onto it as needed, while encouraging smaller passenger cars to slow down and stay within the travel lane. Mountable islands were also installed at the College Drive and Matteson Road approaches, as their gently sloped design provides large vehicles with additional maneuvering space while maintaining safety for all users.

Roundabout Visualization Video

Click here or on the graphic below to view a visualization of how traffic, including trucks, is expected to move around the new VT 67A roundabout. 

2025 Construction Season Highlights

In 2025, crews completed the majority of work needed to build the new VT 67A single‑lane peanut‑shaped roundabout and its connecting roadways. Early in the season, drainage infrastructure was installed along VT 67A, and the roadway was temporarily widened to the south to maintain traffic flow while crews built the northern half of the roundabout and reconstructed the approaches on College Drive and Matteson Road, including drainage and mountable island installation.



Then, crews reconstructed the Silk Road approach to the roundabout and constructed the inner and outer rings of the center peanut roundabout, including the stamped concrete truck apron. Sidewalk along College Drive and VT 67A, and the shared‑use “ninja” path between VT 67A and Silk Road were constructed. With these major elements in place, the new VT 67A roundabout opened to traffic on Friday, November 14, 2025.

Current Conditions & What to Expect

The VT 67A roundabout at College Drive, Matteson Road, and Silk Road is open to traffic, but the area remains in a temporary condition while construction is paused for the winter. Drivers should use extra caution and slow down, as the pavement surface, splitter islands, and other roundabout features are not yet complete and permanent pavement markings are not in place. The speed limit approaching and traveling through the roundabout is 25 MPH.


Permanent roadway signs are installed to guide drivers through the roundabout, and additional temporary signs and devices are in place to alert motorists to the temporary construction conditions. The splitter island on the Silk Road approach has not yet been built; a sign marks its future location.

2026 Construction Plans

Construction will resume in spring 2026, with project completion expected in summer 2026. Work next season will include finishing the VT 67A and Silk Road splitter islands, placing the final wearing course of pavement, installing permanent line striping and pavement markings, completing streetlight installation, finishing the stormwater retention pond, and completing landscaping, sign installation, general cleanup, punch list items, and demobilization. An email project update will be issued before crews return in the spring, and weekly Construction Updates will resume during active construction next season.

Stay Informed

The Bennington Roundabout Project team sends weekly email Construction Updates during active work, timely Traffic Alerts when schedules or travel conditions change significantly, and important Project Announcements as key milestones are reached. Email updates are the fastest and most reliable way to stay informed about construction progress, traffic impacts, and the overall project timeline. You can sign up anytime by completing this online form or contacting the project’s Public Information Consultant.

Contact Information

Questions or comments about the Bennington Roundabout Project? Contact the project’s Public Information Consultant, Elaine Ezerins, anytime by email at elaine.ezerins@wsp.com or by phone at (603) 782-2460.

Facebook  Twitter  Instagram  

To learn more about VTrans Construction Projects, visit our projects website.